Project Metrics

245 MW
Estimated Capacity
$10.00B
Estimated Investment

Ownership & Power

  • Developer Hut 8

Project Timeline

Dec 17, 2025

Project announced

Jun 28, 2027

Expected opening

Data Confidence & Evidence

    Verified Project

Analyst Notes

$7.0B is lease contract value (revenue, not capex); the $10B figure is LED's stated Phase I project investment. 'Google, a subsidiary of Alphabet Inc., is providing a financial backstop'; Fluidstack holds 'a Right of First Offer (ROFO) for up to an additional 1,000 MW of IT capacity.' Entergy providing '330 MW of utility capacity for the campus.' Initial data hall 'scheduled for completion and commissioning in Q2 2027.' Financed partly via $3.25B bond sale. Hut 8's GPU vertical operates as Highrise AI.

Project Information

  • Project Type HYPERSCALE CAMPUS
  • Lifecycle Stage Construction
  • Status UNDER CONSTRUCTION
  • Country United States
  • State / Region Louisiana
  • City West Feliciana Parish (near St. Francisville)

Ownership

  • Ticker HUT

Location