Project Metrics

240 MW
Estimated Capacity
104,000
Estimated GPUs

Ownership & Power

  • Developer Nscale

Compute Infrastructure

  • Estimated GPU Count 104,000
  • GPU Model NVIDIA GB300 NVL72

Project Timeline

Oct 15, 2025

Project announced

Data Confidence & Evidence

Analyst Notes

Site leased from Ionic Digital; fourth Nscale–Microsoft deal, reported at up to $24B (contract value, not capex). Construction from Q3 2026; Microsoft holds an option for a further 700 MW from Q1 2027. 240 MW initial, expandable to 1.2 GW; basis unstated. GPU count is the announced deployment plan.

Project Information

  • Project Type GPU CLUSTER
  • Status ANNOUNCED
  • Country United States
  • State / Region Texas
  • City Barstow

Location