Project Metrics

103 MW
Estimated Capacity

Ownership & Power

  • Developer SK Telecom

Project Timeline

Jun 21, 2025

Project announced

Nov 30, 2027

Expected opening

Data Confidence & Evidence

    Verified Project

Analyst Notes

Groundbreaking Aug 2025; AWS anchor tenant. First phase 41 MW by Nov 2027, expanding to 103 MW by Feb 2029; basis unstated. The $5.88B figure is AWS's Korea-wide investment, so no site capex is recorded. SKT's July 2026 15 GW-by-2035 regional plan is aspirational and not recorded.

Project Information

  • Project Type HYPERSCALE CAMPUS
  • Lifecycle Stage Construction
  • Status UNDER CONSTRUCTION
  • Country South Korea
  • State / Region Ulsan
  • City Ulsan

Ownership

  • Ticker SKM

Location