Project Metrics

90 MW
Estimated Capacity
$540.00M
Estimated Investment

Ownership & Power

  • Developer eStruxture Data Centers

Project Timeline

Oct 29, 2024

Project announced

Dec 31, 2026

Expected opening

Data Confidence & Evidence

    Verified Project

Analyst Notes

Tier III design, up to 125kW/rack densities. CoreWeave signed as Phase 1 anchor tenant May 14, 2026 — its second Canadian site. eStruxture frames CAL-3 as part of 'more than C$1 billion' Alberta investment; capex here is the CA$750M (US$540M) CAL-3 figure.

Project Information

  • Project Type COLOCATION
  • Lifecycle Stage Construction
  • Status UNDER CONSTRUCTION
  • Country Canada
  • State / Region Alberta
  • City Rocky View County (Calgary area)