Project Metrics

1,000 MW
Estimated Capacity
$15.00B
Estimated Investment

Ownership & Power

  • Developer Google

Project Timeline

Oct 14, 2025

Project announced

Dec 31, 2028

Expected opening

Data Confidence & Evidence

    Verified Project

Analyst Notes

Google's largest AI hub outside the US; $15B over 2026–2030 includes subsea cable gateway and clean energy. Foundation laid April 2026. 1 GW is 'compute capacity' with basis unstated. Partners AdaniConneX and Nxtra.

Project Information

  • Project Type HYPERSCALE CAMPUS
  • Lifecycle Stage Construction
  • Status UNDER CONSTRUCTION
  • Country India
  • State / Region Andhra Pradesh
  • City Visakhapatnam

Ownership

  • Ticker GOOGL

Location

Back to Results