Project Metrics

750 MW
Estimated Capacity

Ownership & Power

  • Developer IREN

Compute Infrastructure

  • GPU Model NVIDIA GB300

Project Timeline

Nov 03, 2025

Project announced

Dec 31, 2026

Expected opening

Data Confidence & Evidence

    Verified Project

Analyst Notes

'750 MW campus located in Childress, Texas.' $9.7B is contract value (cloud services revenue), not capex — capexUsd null; hardware funded partly via '$5.8 billion' Dell purchase agreement and a 20% Microsoft prepayment. Site began as grid-connected bitcoin campus (345kV). Horizon 1 (first GB300 cluster) handover targeted Q3 2026.

Project Information

  • Project Type HYPERSCALE CAMPUS
  • Lifecycle Stage Construction
  • Status UNDER CONSTRUCTION
  • Country United States
  • State / Region Texas (Childress County)
  • City Childress

Ownership

  • Ticker IREN

Location