Project announced
Expected opening
Gas turbines rated up to ~300 MW are reported on site, bridging the gap while grid capacity is built. CORRECTION 2026-08-01: the previous 300 MW confirmed figure was Epoch's April total-facility-power estimate, which Epoch itself revised. Oracle stated 'In Abilene, 200MW is already operational' (April 2026) — that operator statement is what the confirmed column now carries. Epoch's live directory estimates 421 MW IT across Buildings 1–4 (May 2026), projecting 843 MW / all eight buildings by ~November 2026; recorded as a separate estimate. OpenAI capped the site at 1.2 GW in March 2026.